Look ahead.
Stay ahead.

The four-week look-ahead, run by your engineers not a spreadsheet.
One source of truth: automated Daily Planner and Bookings, with Roadblocks surfaced early.

Everything runs off
one engine.

The Baseline look-ahead isn’t a static plan it’s your planning engine, live. Change it once and everything downstream follows: dates, bookings and the daily planner.

Daily
Planner

The program, collapsed into today. Due, overdue and closed at a glance with every roadblock, material, subcontractor and conformance owned and dated, so nothing slips between weekly updates.

Daily Ops · Sunday 31/05/2026

RE3210 — Bruce Hwy Upgrade

v1
0 Active · 3 Overdue · Refresh 14:18
REFRESH
Due Today
02
▲ +2 vs yesterday
Overdue
03
▼ −4 vs yesterday
Closed Today
01
1 of 5 targeted
Active Activities
00
#
ACTIVITY
RESOURCE
SHIFT
START
FINISH
ACTIONS
WK OF 31 MAY
SUN
31
TODAY
MON
1
TUE
2
WED
3
THU
4
FRI
5
SAT
6
STAGE 2: DRAINAGE & STRUCTURES
RCP INSTALL
18
RCP installation Ch 4700
Drainage 1
DAY
1 June
2 June
19
Pits P1-P5
Drainage 1
DAY
3 June
4 June
General3 items1 OVERDUE1 DUE TODAYARCHIVE
Description
Assignee
Due
Submit EOT003
Sham
29 / 05 / 2026
Update Variations Register
Sam
31 / 05 / 2026
RPEQ Design for Sweep Path Analysis
Cody
03 / 06 / 2026
Roadblocks2 items1 OVERDUE1 DUE TODAYARCHIVE
Status
Type
Description
Activity
Assignee
Due
OPEN
MATERIALS
RCP 600mm delivery delayed 5 working days — Humes Pipes manufacturing backlog
RCP installation Ch 4500
Alex B
14 / 05 / 2026
OPEN
RFI
Pit P3 — clarification needed on invert level vs DM design (drawing C-2107 rev B)
Pits P1-P5
Todd
31 / 05 / 2026
Materials3 itemsALL CLEARARCHIVE
Status
Description
Activity
Qty
Supplier
Assignee
Due
NEEDS UPDATE
RCP 450mm class 3
RCP installation Ch 4700
95 m
Humes Pipes
Brendon
01 / 06 / 2026
NEEDS UPDATE
N32/20 concrete — RCBC wall pour
RCBC pour — walls
18 m³
Holcim Concrete
Brendon
02 / 06 / 2026
DRAFT
Crushed rock — Type 1 sub-base
Sub-base placement
1800 t
Wagners
Sham
10 / 06 / 2026
Subcontractors1 itemALL CLEARARCHIVE
Status
Description
Activity
Period
Resource
Assignee
Due
NEEDS UPDATE
Confirm Downer — Intermediate asphalt (04/06–08/06)
Intermediate asphalt
04/06 – 08/06
Downer
Tom
04 / 06 / 2026
Conformances1 item1 OVERDUEARCHIVE
Description
Activity
Assignee
Due
Survey, Proof Roll, HP Release
Subgrade preparation
Unassigned
29 / 05 / 2026
Roadblocks · Saturday 30 May 2026

RE3210 — Bruce Hwy Upgrade

v1
1 Open in this view · 1 Overdue · Avg resolve 9.7
Open
01
Roadblocks across program
Overdue
01
Past required-by date
Avg days to resolve
9.7
Rolling 30-day window
ROADBLOCKSSTATUS:OPENALLRESOLVEDCLEAR FILTERS
Status
Type
Description
Activity
Due
Assignee
Actions
RESOLVED
MATERIALS
RCP 600mm delivery delayed 5 working days — Humes Pipes manufacturing backlog
RCP installation Ch 4500
14 / 05 / 2026RESOLVED
Alex B
Reopen
RESOLVED
RFI
Pit P3 — clarification needed on invert level vs DM design (drawing C-2107 rev B vs as-built survey)
Pits P1-P5
18 / 05 / 2026RESOLVED
Todd
Reopen
OPEN
NCR
RCBC wall pour failed 7-day compressive strength test (target 32 MPa, achieved 24 MPa)
RCBC pour — walls
22 / 05 / 20268 DAYS OVERDUE
Alex B
RESOLVE
RESOLVED
APPROVAL
Asphalt mix design (AC14 60/70 binder) awaiting DTMR TIE engineer approval
Intermediate asphalt
26 / 05 / 2026RESOLVED
Emma
Reopen

Roadblocks

Every blocker materials, RFIs, NCRs, approvals surfaced, owned and dated. Tracked from raised to resolved, with the overdue ones impossible to ignore.

Bookings · Saturday 30 May 2026

RE3210 — Bruce Hwy Upgrade

5 Drafts · 2 Confirmed · 13 Needs attention
Open drafts
05
Awaiting confirmation
Confirmed
02
Bookings locked in
Needs attention
13
Draft + needs update
Avg confirm days
14.7
Rolling avg to confirm
MaterialsSubcontractorsAllNeeds attentionContacts
BOOKINGS REGISTERADD MATERIALS BOOKINGEMAIL THIS SUPPLIERSELECT MULTIPLECLEAR FILTERS
Status
Date
Supplier
Description
Activity
Qty
UOM
Notes
Assignee
Actions
NEEDS UPDATE
25/05/20265 days overdue
OneSteel Reinforcing
N16 reinforcement bar — 6 m lengths
RCBC excavation
12
tonne
Brendon
CONFIRMED
27/05/20263 days overdue
Humes Pipes
RCP 600mm class 4 reinforced concrete pipe
RCP installation Ch 4500
120
m
Brendon
CONFIRMED
29/05/20261 day overdue
Holcim Concrete
N32/20 concrete — RCBC base pour
RCBC pour — base
25
Brendon
NEEDS UPDATE
01/06/2026in 2 days
Humes Pipes
RCP 450mm class 3
RCP installation Ch 4700
95
m
Brendon
NEEDS UPDATE
02/06/2026in 3 days
Holcim Concrete
N32/20 concrete — RCBC wall pour
RCBC pour — walls
18
Brendon
DRAFT
10/06/2026in 11 days
Wagners
Crushed rock — Type 2.3 sub-base
Sub-base placement
1,800
tonne
Sham
DRAFT
17/06/2026in 18 days
Boral
AC14 intermediate course asphalt
Intermediate asphalt
340
tonne
Sophie

Booking
Reservations

Every supplier booking materials, plant, subcontractors drafted, confirmed and tracked. From request to delivery, with the unconfirmed ones surfaced before they bite.

They do a slice.
Baseline does the lot.

Excel tracks, P6 and Asta schedule. None of them run a site week.
Baseline covers the whole four-week loop and automates most of it.

Capability BaselineExcelP6Asta
Predecessor graph (multi-pred, governing rule)
Working-day calendars (3-layer)
Project-specific rosters
Slip cascades automatically
Critical path highlighted in one click
Materials & productivity per activity
Bookings, Roadblocks & Daily Planner auto-populated from the program
Subbie-filtered PDF export
Key-milestone slip flagged in the report
Weekly report flags what needs action
Real-time multi-user editing

Run your next four weeks on Baseline.

4 slots1 takenQLD firstNo contract